Storefront with a giant old-fashioned red price tag with  price flipped away from view

Before You Buy Commercial Property | Nashville, TN | Commercial GC Guide

November 23, 2026•9 min read

Quick answer: Before you buy commercial property in Nashville, confirm ten construction conditions: utility capacity, zoning, site access, drainage, soils, rock, the existing building, fire protection, electrical service and ADA. Each one can add cost or months to a project, and none of them shows up in the listing price. A commercial General Contractor can review all ten during your due diligence period, before you close.

A listing tells you the price, the acreage and the traffic count. It rarely tells you that the nearest sewer line is 800 feet away, that limestone sits two feet below the parking lot, or that the building needs a new fire line before anyone can occupy it. Those conditions decide what the property will really cost you, and most of them are cheaper to find before closing than after.

Nashville adds its own variables. Metro zoning and overlay districts, Metro Water Services capacity reviews, stormwater rules and Middle Tennessee's shallow limestone all shape what a site can support and what it will take to build there. If you are weighing a parcel or an existing building in Davidson County, these are the ten questions we ask on every pre-purchase review. For a broader look at budgets, see The Real Cost of Commercial Construction in Nashville.

The 10 construction questions to ask before you buy

1. Are water, sewer, gas and power available, and do they have capacity?

Availability and capacity are separate answers. A water main can run along the frontage and still be too small for your sprinklers or your process load. Ask where each utility connects, how far the tie-in is and who owns the line.

In Davidson County, commercial projects need a capacity determination from Metro Water Services before construction starts. The Multifamily and Commercial Development Guide describes the availability request, a capacity study of about 15 working days and capacity fees paid in installments. Start that request during due diligence so you know the answer and the fee before you close.

Ask for: utility locations and sizes, the distance to each tie-in, a Metro Water Services availability response and estimated capacity and tap fees.

2. Does the zoning allow your use, at the size you need?

Zoning decides what you can operate on the property, how much you can build, how tall and how much parking you need. Check the base district first, then any overlay or Specific Plan (SP) that adds its own rules. Metro's Parcel Viewer shows a parcel's current zoning, and Metro Codes explains how to read the land use tables in Understanding the Zoning Code.

If your use needs a rezoning, a variance or a special exception, plan for public hearings and several months of schedule.

Ask for: the zoning district, overlays, permitted uses, setbacks, height limits, parking requirements and any conditions recorded on the parcel.

3. Can trucks, customers and fire apparatus get in and out?

Access drives the site layout and the budget. A commercial site may need new curb cuts, a turn lane or a traffic study before Metro approves the driveway. Delivery trucks need turning room, and the fire department needs a clear route to the building.

Driveway and right-of-way work in Nashville goes through the Nashville Department of Transportation (NDOT developer resources).

Ask for: existing curb cuts, shared access easements, sight distance at each entrance and whether a traffic study is likely.

4. Where does the water go when it rains?

Every new roof and parking lot adds runoff, and Metro requires you to manage it. Projects in Metro's MS4 area must meet the Low Impact Development standard for water quality and volume, according to the Metro Water Services Stormwater Development Guide. That can mean detention, bioretention or underground storage, and each one takes land or budget.

Walk the site after a heavy rain if you can. Standing water, erosion and a low corner at the property line are early warnings.

Ask for: floodplain status, existing drainage paths, downstream easements and room on the site for a detention area.

5. Will the soil support the building?

Soil determines what kind of foundation the building needs. Expansive clay, soft fill or a high water table can turn a standard spread footing into piers, undercutting or ground improvement. The USDA Web Soil Survey gives a first look at mapped soil types, but only a geotechnical investigation tells you what sits under your footprint.

Order borings during due diligence, before your option period ends.

Ask for: a geotechnical report with boring logs, the recommended foundation type and bearing capacity and any notes on undocumented fill.

6. How deep is the rock?

Middle Tennessee sits on limestone, and in many parts of Davidson County it is close to the surface. Shallow rock affects foundations, utility trenches, detention ponds and elevator pits. Removing it by ripping, hammering or blasting adds equipment, time and cost, and it is a common source of change orders on Nashville sites.

The same geotechnical borings should record the depth to rock across the site. For more on how crews handle it, read What Happens When a Commercial Construction Project Encounters Rock, Bad Soil, or an Underground Surprise?

Ask for: depth to rock at each boring, rock quality notes and a unit price for rock removal in the construction estimate.

7. What condition is the existing building really in?

An existing building can save months, or it can hold the largest costs on the property. Look past the finishes to the roof, structure, slab, MEP systems and building envelope. Ask whether the building meets current code for your intended use, because a change of occupancy can trigger upgrades to egress, fire separation and structure.

Bring a General Contractor and the right trades on the walk-through.

Ask for: roof age and warranties, as-built drawings, recent inspection reports, any asbestos or lead survey and the replacement dates of the HVAC and electrical equipment.

8. Does the property have the fire protection your use requires?

Your use, building size and construction type decide whether you need sprinklers, a fire alarm, a fire pump or more hydrants. If the building needs a new or larger fire line, that work reaches back to the water main, and the available fire flow may fall short without upgrades.

The Nashville Fire Marshal's Office reviews fire alarm and suppression plans for commercial projects (Fire and Life Safety Codes Plan Review).

Ask for: existing sprinkler and alarm system details, hydrant locations, fire flow test results and the latest inspection report.

9. Is there enough electrical capacity for your operation?

Many older commercial buildings have electrical service sized for light office use. A restaurant, medical office, light manufacturing space or EV charging can need much more power, often three-phase service. An upgrade may require a new transformer, new switchgear and coordination with Nashville Electric Service, and equipment lead times can run long.

NES publishes its requirements for commercial service in its Electric Service Guidelines.

Ask for: the existing service size and voltage, the transformer location, available capacity from NES and the age of the main electrical equipment.

10. What will ADA compliance require?

New construction must meet the 2010 ADA Standards for Accessible Design, and renovations carry obligations too. When you alter an area of primary function, the path of travel to it, including restrooms, must be made accessible. The Department of Justice's guidance on the 2010 Standards treats that cost as disproportionate when it exceeds 20 percent of the cost of the alteration.

Accessible parking, ramps, entrances, door hardware and restrooms are common gaps in older buildings.

Ask for: an accessibility review of the parking, route, entrance and restrooms, priced before you set the renovation budget.

Where site-development costs hide

Most of these costs land in site work and building upgrades, before any new square footage goes up. Use this table as a due diligence checklist

Custom HTML/CSS/JavaScript

Once you have these answers, carry a contingency for what borings and walk-throughs cannot show. Our guide to change orders and preconstruction explains how early planning reduces surprises once work begins.

Bring a General Contractor in before you close

The best time to involve a commercial General Contractor is during your due diligence period, while you can still renegotiate the price or walk away. A General Contractor reads a site the way a crew will build it: where the trench runs, where rock is likely, how the trucks will turn and what the fire line will cost.

Beech Construction Services has built in Nashville since 1993. Our team self-performs site work, utility excavation and concrete, so we price those risks from field experience. On a pre-purchase review, we walk the property with you, read the geotechnical and survey data, flag the conditions on this list and give you a budget range you can take into negotiations. You can see the kinds of commercial and industrial projects we deliver and the full list of services.

Looking at a property in Nashville or Middle Tennessee? Contact Beech Construction Services to schedule a pre-purchase site review with our team.

Frequently asked questions

What is construction due diligence for a commercial property?

Construction due diligence is the review of a property's physical conditions before you buy it. It covers utilities, zoning, access, drainage, soils, rock, the existing building, fire protection, electrical service and ADA. The goal is to price what it will take to build or renovate for your use before the purchase is final.

When should I bring a General Contractor into a commercial property purchase?

Bring a commercial General Contractor in during your due diligence or option period, before closing. At that stage, findings about rock, utilities or code upgrades can still change your offer, your budget or your decision to buy.

How do I find the zoning for a property in Nashville?

Search the address in Metro Nashville's Parcel Viewer to see the zoning district and any overlays. Then check the permitted uses in Title 17 of the Metro Code, and confirm questions with Metro Codes or Metro Planning before you rely on them.

Do I need a geotechnical report before buying commercial land?

Yes, if you plan to build on it. A geotechnical report with soil borings tells you the bearing capacity, the depth to rock and the foundation type the building needs. In Middle Tennessee, shallow limestone makes this report one of the most valuable studies in due diligence.

Does an existing building have to meet current ADA standards when I renovate?

Altered areas must meet the 2010 ADA Standards. When you alter an area of primary function, the path of travel to it, including restrooms, must also be made accessible. DOJ guidance treats that path of travel cost as disproportionate when it exceeds 20 percent of the alteration cost.

How long does a Metro Water Services capacity study take?

Metro Water Services lists about 15 working days for a water and sewer capacity study on commercial developments, according to its Multifamily and Commercial Development Guide. Capacity fees are paid in installments after the permit is issued.

Beech Construction Services

Beech Construction Services

Beech Construction Services brings over 30 years of experience delivering high-quality construction and renovation projects across commercial, residential, and industrial sectors. Known for our craftsmanship, professionalism, and client-first approach, we’re passionate about building spaces that stand the test of time.

LinkedIn logo icon
Back to Blog

© Copyright 2025 Beech Construction Services. | All Rights Reserved. | Designed by Topline

Legal

Contact Info

Address: 541B Huntley Industrial Blvd, Smyrna, TN 37167

Get updates, project highlights, and insights straight to your inbox.

© Copyright 2025 Beech Construction Services. | All Rights Reserved. | Designed by Topline